Shifts with one or two stretches
A shift is a list of the stretches of the day somebody works. There are two shapes, and the difference between them only shows up on the day somebody forgets to punch — which is exactly when it is too late to change your mind.
- One stretch a day — Two punches a day. The midday break is deducted automatically.
- Morning and afternoon — Four punches a day. A miss scan costs half a day instead of the whole one.
A shift that runs past midnight is simply one whose end is earlier than its start. There is no separate setting for it, and the whole night counts against the day it began.
Before you start
- The
attendance.configurepermission. The Owner and HR roles hold it.
Steps
- Open Shifts and press Add a shift.
- Give it a Name staff will recognise on their own phone — "Day shift", "Night shift".
- Choose one stretch or two.
- Fill in Starts and Ends for each.
- Set Counts as: the hours the stretch is worth. This is not always the time between the two — a shift of 08:00 to 17:00 with an hour for lunch counts as 8, not 9.
- Choose the Day value: 1 day or ½ day. Leave it at 1 day unless the company counts this shift as less — see below.
- Press Save the shift.
Naming the stretches
Each stretch has a Stretch name: Morning, Midday, Afternoon, Evening or Night. It is what staff read in the Mini App, on the clock-in button and in their history, and on the Telegram approval cards, each in their own language. Left on By order, two stretches are called Morning and Afternoon and a single one has no name. The name is a label only: it changes nothing about how the day is counted. Change it later with Edit.
What you should see
The shift appears in the list with its hours, and a shift that crosses midnight is marked Ends the next day.
Nothing happens to anybody's attendance yet. A shift has to be assigned before it applies to a person — see Deciding who works which shift.
What a day on the shift is worth
Every shift counts for 1 day unless you set it to ½ day, whether it has one stretch or two. That one figure decides three things:
- Worked. A full day on the shift adds its day value to the days worked.
- Missed. An unpaid absence costs the day values of the stretches that were missed.
- On leave. A day of leave takes the shift's day value from the balance. Rest days and public holidays take nothing.
A two-stretch shift splits its day value evenly between the two stretches. At 1 day, the morning and the afternoon are half a day each; at ½ day, each is a quarter.
The day value is not the hours. Counts as still says how many hours a stretch is worth, and the hourly rate for overtime still comes from the standard hours of the shift the person works on most days.
Example: a Saturday morning counted as a whole day
Many companies work Saturday mornings and count them as a full day. Create a one-stretch shift called "Saturday morning", 08:00 to 12:00, with Day value at 1 day, and put it on Saturday in the branch's week, with Sunday left on Rest — see Deciding who works which shift. Then:
- Working the morning counts as 1 day.
- Missing it costs a whole day's pay: $20.00 on a $520.00 salary with the usual divisor of 26. See The daily rate.
- Annual leave on that Saturday takes 1 day from the balance.
Changing it later
Each shift in the list has its own Day value, and choosing a different one saves it at once. The day records of every attendance period that is not locked yet are recalculated. A locked period keeps the value it was locked with, and a leave request already filed keeps the day count it was filed with. The change is written to the activity log.
When a late start is made up by the end of the day
By default a late arrival is late, however late the person then stayed. A company that prefers to count the day as a whole switches on No late or early-leave minutes on a day worked in full under Settings → Attendance. From then on, a day whose worked minutes — clock-out minus clock-in, stretch by stretch — reach the scheduled length of its stretches shows no late or early-leave minutes at all: thirty minutes late and thirty minutes over is a full day, with no mark and no late penalty.
The comparison is with the stretch from its start to its end, not with what the day is worth. A stretch of 08:00–17:00 is nine hours long whatever its credit, so arriving at 09:00 and leaving at 17:00 is still an hour late. A stretch that is missing a punch has no worked minutes to count, so it cannot be made up for by the other stretch, and a stretch on approved leave is left out on both sides. Switching the setting either way recalculates every day of every period that is not locked, and the activity log keeps who did it and how many days changed.
Fixing a shift's times, or deleting it
Press Edit on the shift. Its name, the start and end of each stretch and the hours each Counts as can all be changed there, and Save keeps them. New times recalculate the days on the shift in every period that is not locked; a locked period keeps the times it was locked with. A shift with one stretch cannot become one with two — add a new shift and put it on the week instead. The change, with the times before and after, is written to the activity log.
Delete removes a shift only while nothing uses it: nobody has worked it, and it is on no weekly schedule, written day or default of a branch, unit or person. Otherwise it stays, so the days already counted on it can still be read. To stop using one, take it off the weekly schedules and defaults.
If something goes wrong
Somebody is marked absent for a whole day when they worked the morning. They are on a one-stretch shift and missed one punch. On a two-stretch shift the morning would have been counted and only the afternoon lost.
A night shift is showing up on the wrong day. It counts against the day it started, so somebody arriving at 22:00 on Monday and leaving at 06:00 on Tuesday appears on Monday. That is deliberate: it keeps one night in one row.
Late minutes are counted from an hour nobody works. Each stretch has its own start, so the afternoon's lateness is measured from the afternoon's start. Check the times on the right stretch.
The hours look wrong on the payslip. Counts as is what a full day of that stretch is worth, and it is what pay is worked out from. The clock time between the two only affects whether somebody was late or left early.
Last checked 04/11/2026